At the 10/13/20 Town Board meeting, the Town received an update from the Town Engineer as follows:
- The Town worked with Westchester County Planning to finalize the terms of their $10M funding commitment. The project was modified to include the Town furnishing package pump systems to residents that will be connecting to low-pressure pump systems.
- At an estimated cost of $8,000 per unit x 130 units, the Town cost would be $1,040,000. This cost was assigned as part of the project contingency and is not changing the overall project cost estimate of $14.3M
- See Revised Cost Table, dated July 2020
- The NYCDEP gave re-approval that the Yorktown project is eligible for the $10M in funding as part of the Watershed agreement.
- The County is working to complete the Right-of-Objection process, which states the $10M in funding will be made available to Yorktown. Other affected agencies and interested parties have a 30-day window to object. Once the project moves past this step, a term sheet and Draft Inter-Municipal Agreement will be prepared by the County Law Dept and sent to Yorktown for review and action.
- The Town is continuing to perform rehabilitation of wastewater pump stations:
- Pump station work complete: Walden Woods, Jefferson Valley, Jefferson Park
- Pump station work commenced: Crystal Lake, Hanover, Mohansic, Salem
- The Town is continuing to perform work within the collection system; cleaning & cctv of pipelines, smoke testing, manhole inspection etc. to demonstrate compliance with CMOM requirements.
- The work described above will assist the Town when applying for an increase in the SPDES discharge permit.